| 
   
   
KEYWORDS: Payment - Pay-when-Paid Clauses, Smith and Smith Glass Ltd -v-
  Winstone Architectural Cladding Systems Ltd (1991), Thomas Dyer & Co -v-
  Bishop International Engineering Co [1968], Durabella Limited -v- J. Jarvis
  & Sons Limited (September 2001), pay-when-paid clauses, Housing Grants
  Construction and Regeneration Act 1996, 
 | 
 
  | 
   
  
   
SUMMARY
In 
  Durabella Limited -v- J. Jarvis & Sons Limited (September 2001)  it
  was held that the 1996 Act clearly envisaged that pay-when-paid clauses which
  shared the risk of insolvency were not unreasonable.    
  A contractor cannot rely on a pay-when-paid clause if the reason for
  non-payment is its own breach of contract or default.  A party cannot
  take an advantage from its own breach of contract.  
  A pay-when-paid could only be effective so long as the main contract
  machinery of payment was capable of being operated.  For the clause to
  be effective the contractor impliedly undertakes that it will pursue all means
  available to obtain payment, or it will not be able to rely on the clause to
  defeat the subcontractors claim for payment.  
  One interesting observation in Durabella was that Section 113(1) of the 1996
  Act did not affect payment conditional on certificates under the main
  contract, the parties freedom to make such arrangements was stated to be
  legitimate and not unreasonable. 
Contractors and subcontractors in the construction industry know the real
  meaning of the famous phrase cashflow is the lifeblood of the industry. A
  contractor who pays a sub-contractor before being paid by the Employer, is
  effectively funding the project.   Add to this the cost of pursuing the
  Employer for non-payment and the precarious nature of construction becomes
  obvious.  Insolvency of the Employer in that situation can threaten the
  continued existence of the contractor.  
  A pay-when-paid Clause means that a subcontractor may have completed the
  SubContract Works in accordance with the SubContract, but is not paid because
  of matters not connected with the SubContract. The Employer may for instance
  withhold payment because of default by the contractor or other
  subcontractors.  
  Not surprisingly, contractors argue that pay-when-paid clauses are a valid
  and legitimate protection against these risks, which are more marked in the
  present lurch of the economy to recession.  
  The subcontractor on the other hand has an equally valid argument against
  pay-when-paid clauses.  If he has properly carried out the work, he
  argues, he should be entitled to be paid, otherwise he will run the risk of
  continued existence instead of the contractor.  He should not become
  embroiled in disputes between the Employer and contractor, which may have
  nothing at all to do with his work.   That situation would be unreasonable
  says the subcontractor and the Housing Grants Construction and Regeneration
  Act 1996 is an indication that cashflow of subcontractors should be
  protected.  
  Courts appear to dislike pay-when-paid clauses and have adopted an
  interpretation to reduce their impact.  In the New Zealand decision in Smith
  and Smith Glass Ltd -v- Winstone Architectural Cladding Systems Ltd (1991)
  a distinction was made between an 'if' clause and a 'when' clause.  An
  'if' clause requires the contractor to pay the subcontractor only when he has
  received payment from the Employer. The 'when' clause indicates the time
  for payment only, so that the time for payment to the subcontractor is
  calculated from the date when payment should have been made by the Employer,
  whether or not payment has in fact been made.  It was held that unless
  the clause spells out in clear and precise terms that payment will not be
  made until payment is received, the clause does no more than indicate the
  time for payment.  
  The US Courts have taken a much more robust approach in reducing the
  effect of pay-when-paid clauses. In Thomas Dyer & Co -v- Bishop
  International Engineering Co [1968] a pay-when-paid clause was held only
  to postpone payment for a reasonable time, to allow the contractor to obtain
  funds to pay, following the Employers failure to pay.  
  The English courts have not followed either approach, but have taken the
  lead from the enactment of the Housing Grants Construction and Regeneration
  Act 1996.  
  Section 113 of the 1996 Act makes unenforceable pay-when-paid clauses of
  the if type, in construction contracts to which the Act applies, except in
  the case where non-payment is due to insolvency of the Employer. 
  Section 113 deals also with the situation where the main contract includes a
  pay-when-paid clause which is dependant on another person making
  payment.  If that other person becomes insolvent, and the Employer does
  not make payment, then the contractor is not under an obligation to make a
  related payment, provided the SubContract pay-when-paid clause is in suitable
  terms.  
  The recent decision in Durabella Limited -v- J. Jarvis & Sons
  Limited (September 2001) now establishes the position in English
  Law.  It was held that the 1996 Act clearly envisaged that pay-when-paid
  clauses which shared the risk of insolvency were not unreasonable. Such
  clauses would therefore be enforced. In my view, unless a contract falls
  under the 1996 Act, it will be difficult now to argue against enforcement of
  any pay-when-paid clauses on grounds of unreasonableness.  
  The decision does not open the floodgates for pay-when-paid clauses. There
  are a number of sensible legal safeguards identified in the decision. 
  First, it was held that a contractor cannot rely on a pay-when-paid clause if
  the reason for non-payment is its own breach of contract or default.  A
  party cannot take an advantage from its own breach of contract.  Second,
  it was held that a pay-when-paid could only be effective so long as the main
  contract machinery of payment was capable of being operated.  It was an
  implied condition for the operation of such a clause.  If the machinery
  breaks down as for instance where certificates are not or cannot be issued as
  they should be, then the contractor was best placed to remedy the
  situation.  For the clause to be effective the contractor impliedly
  undertakes that it will pursue all means available to obtain payment, or it
  will not be able to rely on the clause to defeat the subcontractors claim for
  payment.  
  The second safeguard was applied to the particular facts of the case in Durabella. 
  Termination of the contractors employment with the Employer prevented further
  payment.  The contractor had failed to pursue its remedies promptly and
  effectually.  It was held that the contractor could not rely on the
  pay-when-paid clause.  
  One interesting observation in Durabella was that Section 113(1) of
  the 1996 Act did not affect payment conditional on certificates under the
  main contract, whether by Architect or Engineer under the contract. 
  This confirms the view generally taken by legal commentators.  The
  parties freedom to make such arrangements was stated to be legitimate and not
  unreasonable.  
  
 
  
The approach
  to be taken by a subcontractor faced with non-payment and a pay-when-paid
  clause can be stated in summary as follows:  
  1.  Establish by legal advice whether the clause is an if clause i.e.
  conditional on payment, or a when clause i.e. setting the time for payment
  only;  
  2.  If the clause is an if clause, then establish  
       (a) whether the non-payment is due to the
  contractors default if so he may not be able to enforce the clause; or  
       (b) whether the non-payment is due to the breakdown
  of the main contract administration if so the contractor may not be able to
  enforce the clause if he has not take steps to enforce his right to payment.  
  3.   If the clause is an if clause, then establish whether your
  contract is caught by the Housing Grants Construction and Regeneration Act
  1996 if so if clauses are unenforceable except in situations of insolvency.
 
 | 
 
No comments:
Post a Comment