Monday, September 9, 2013

Excerpts - Payment - Pay-when-Paid Clauses (Just pasted for reference and have no rights over this article for whatsoever nature)


Payment - Pay-when-Paid Clauses

© Daniel Atkinson 18 November 2001

 
KEYWORDS: Payment - Pay-when-Paid Clauses, Smith and Smith Glass Ltd -v- Winstone Architectural Cladding Systems Ltd (1991), Thomas Dyer & Co -v- Bishop International Engineering Co [1968], Durabella Limited -v- J. Jarvis & Sons Limited (September 2001), pay-when-paid clauses, Housing Grants Construction and Regeneration Act 1996,
 
SUMMARY
In  Durabella Limited -v- J. Jarvis & Sons Limited (September 2001)  it was held that the 1996 Act clearly envisaged that pay-when-paid clauses which shared the risk of insolvency were not unreasonable.  
A contractor cannot rely on a pay-when-paid clause if the reason for non-payment is its own breach of contract or default.  A party cannot take an advantage from its own breach of contract.
A pay-when-paid could only be effective so long as the main contract machinery of payment was capable of being operated.  For the clause to be effective the contractor impliedly undertakes that it will pursue all means available to obtain payment, or it will not be able to rely on the clause to defeat the subcontractors claim for payment.
One interesting observation in Durabella was that Section 113(1) of the 1996 Act did not affect payment conditional on certificates under the main contract, the parties freedom to make such arrangements was stated to be legitimate and not unreasonable.
Contractors and subcontractors in the construction industry know the real meaning of the famous phrase cashflow is the lifeblood of the industry. A contractor who pays a sub-contractor before being paid by the Employer, is effectively funding the project.   Add to this the cost of pursuing the Employer for non-payment and the precarious nature of construction becomes obvious.  Insolvency of the Employer in that situation can threaten the continued existence of the contractor.
A pay-when-paid Clause means that a subcontractor may have completed the SubContract Works in accordance with the SubContract, but is not paid because of matters not connected with the SubContract. The Employer may for instance withhold payment because of default by the contractor or other subcontractors.
Not surprisingly, contractors argue that pay-when-paid clauses are a valid and legitimate protection against these risks, which are more marked in the present lurch of the economy to recession.
The subcontractor on the other hand has an equally valid argument against pay-when-paid clauses.  If he has properly carried out the work, he argues, he should be entitled to be paid, otherwise he will run the risk of continued existence instead of the contractor.  He should not become embroiled in disputes between the Employer and contractor, which may have nothing at all to do with his work.   That situation would be unreasonable says the subcontractor and the Housing Grants Construction and Regeneration Act 1996 is an indication that cashflow of subcontractors should be protected.
Courts appear to dislike pay-when-paid clauses and have adopted an interpretation to reduce their impact.  In the New Zealand decision in Smith and Smith Glass Ltd -v- Winstone Architectural Cladding Systems Ltd (1991) a distinction was made between an 'if' clause and a 'when' clause.  An 'if' clause requires the contractor to pay the subcontractor only when he has received payment from the Employer. The 'when' clause indicates the time for payment only, so that the time for payment to the subcontractor is calculated from the date when payment should have been made by the Employer, whether or not payment has in fact been made.  It was held that unless the clause spells out in clear and precise terms that payment will not be made until payment is received, the clause does no more than indicate the time for payment.
The US Courts have taken a much more robust approach in reducing the effect of pay-when-paid clauses. In Thomas Dyer & Co -v- Bishop International Engineering Co [1968] a pay-when-paid clause was held only to postpone payment for a reasonable time, to allow the contractor to obtain funds to pay, following the Employers failure to pay.
The English courts have not followed either approach, but have taken the lead from the enactment of the Housing Grants Construction and Regeneration Act 1996.
Section 113 of the 1996 Act makes unenforceable pay-when-paid clauses of the if type, in construction contracts to which the Act applies, except in the case where non-payment is due to insolvency of the Employer.  Section 113 deals also with the situation where the main contract includes a pay-when-paid clause which is dependant on another person making payment.  If that other person becomes insolvent, and the Employer does not make payment, then the contractor is not under an obligation to make a related payment, provided the SubContract pay-when-paid clause is in suitable terms.
The recent decision in Durabella Limited -v- J. Jarvis & Sons Limited (September 2001) now establishes the position in English Law.  It was held that the 1996 Act clearly envisaged that pay-when-paid clauses which shared the risk of insolvency were not unreasonable. Such clauses would therefore be enforced. In my view, unless a contract falls under the 1996 Act, it will be difficult now to argue against enforcement of any pay-when-paid clauses on grounds of unreasonableness.
The decision does not open the floodgates for pay-when-paid clauses. There are a number of sensible legal safeguards identified in the decision.  First, it was held that a contractor cannot rely on a pay-when-paid clause if the reason for non-payment is its own breach of contract or default.  A party cannot take an advantage from its own breach of contract.  Second, it was held that a pay-when-paid could only be effective so long as the main contract machinery of payment was capable of being operated.  It was an implied condition for the operation of such a clause.  If the machinery breaks down as for instance where certificates are not or cannot be issued as they should be, then the contractor was best placed to remedy the situation.  For the clause to be effective the contractor impliedly undertakes that it will pursue all means available to obtain payment, or it will not be able to rely on the clause to defeat the subcontractors claim for payment.
The second safeguard was applied to the particular facts of the case in Durabella.  Termination of the contractors employment with the Employer prevented further payment.  The contractor had failed to pursue its remedies promptly and effectually.  It was held that the contractor could not rely on the pay-when-paid clause.
One interesting observation in Durabella was that Section 113(1) of the 1996 Act did not affect payment conditional on certificates under the main contract, whether by Architect or Engineer under the contract.  This confirms the view generally taken by legal commentators.  The parties freedom to make such arrangements was stated to be legitimate and not unreasonable.

 

PRACTICE NOTE 1
The approach to be taken by a subcontractor faced with non-payment and a pay-when-paid clause can be stated in summary as follows:
1.  Establish by legal advice whether the clause is an if clause i.e. conditional on payment, or a when clause i.e. setting the time for payment only;
2.  If the clause is an if clause, then establish
     (a) whether the non-payment is due to the contractors default if so he may not be able to enforce the clause; or
     (b) whether the non-payment is due to the breakdown of the main contract administration if so the contractor may not be able to enforce the clause if he has not take steps to enforce his right to payment.
3.   If the clause is an if clause, then establish whether your contract is caught by the Housing Grants Construction and Regeneration Act 1996 if so if clauses are unenforceable except in situations of insolvency.

No comments:

Post a Comment